96 hour road closure

Please be advised that a full 96 hour road closure will occur on the Main Street Bridge. This closure will occur Tuesday September 11th through Friday September 14th, and will be a full 96 hours.

The detour route for this closure will follow Hammond Avenue, Maureen Street, and Central Avenue (as outlined under the “Detour Routes” section). Please follow all construction and detour signage for the safety of the workers on site.

48 hour road closure | Update

Please be advised that a full 48 hour road closure will occur on the Main Street Bridge. This closure will occur Wednesday September 5th and Thursday September 6th.

 

The detour route for this closure will follow Hammond Avenue, Maureen Street, and Central Avenue (as outlined under the “Detour Routes” section). Please follow all construction and detour signage for the safety of the workers on site.

Please be advised that a full 96 – hour road closure will occur on the Main Street Bridge. This closure will occur Monday August 20th at 7pm to Friday August 24th at 7pm.

Please be advised that a full 96 – hour road closure will occur on the Main Street Bridge. This closure will occur Monday August 20th at 7pm to Friday August 24th at 7pm.

The detour route for this closure will follow Hammond Avenue, Maureen Street, and Central Avenue (as outlined under the “Detour Routes” section). Please follow all construction and detour signage for the safety of the workers on site.

96-hour road closure will occur on the Main Street Bridge.

During the week of Tuesday, August 7th to Saturday, August 11th, please be advised that a full 9 6-hour road closure will occur on the Main Street Bridge. This closure is scheduled to begin Tuesday,  August 7th at 7am on and be completed on Saturday, August 11th.

The detour route for this closure will follow Hammond Avenue, Maureen Street, and Central Avenue (as outlined under the “Detour Routes” section). Please follow all construction and detour signage for the safety of the workers on site.

Two-day partial road closure will occur on the Main Street Bridge.

During the week of Monday, June 11th to Friday, June 15th, a two-day partial road closure will occur on the Main Street Bridge.  This road closure is to facilitate work that is being done by Union Gas on the bridge (decommissioning of a gas line).

The Westbound Lane will be closed on Monday June 11th from 7:00am to 8:00pm, and once again will be closed on Tuesday June 12th from 7:00am to 1:00pm. The detour route for this closure will follow Hammond Avenue, Maureen Street, and Central Avenue (as outlined under the “Detour Routes” section). Please follow all construction and detour signage.

Construction Update (Week of May 28th to June 1st)

For the week of Monday, May 28th to Friday, June 1st, there are no scheduled road closures for the Main Street Bridge and traffic will operate under normal conditions in the usual two-lanes.

The current work being done on the bridge is the continuation of the repairing of deteriorated concrete on the piers. These concrete repairs are to continue for the remainder of this week.