Project Details

The City of Thunder Bay has retained LH North General Contractors to complete the Main Street Bridge rehabilitation project. Additionally, WSP Canada Inc. will provide consultant services. The overall project is divided into two separate phases (2018 and 2019). 

The 2018 phase begins on May 14th, 2018 and will continue to November 2018. During this time, some of the major work that is to be completed includes the repairing of deteriorated concrete and the replacement of each sidewalk. In addition to periodic single lane closures, full 48 hour road closures will occur. All notices prior to any closures will be found on this website. 

Following the completion of phase one, the 2019 phase is to begin in April 2019 and continue to August 2019. Significant work to be completed during this phase will include the repairing of asphalt, structural steel, and overall waterproofing. During this phase, full 96 hour closures will be scheduled as per prior notices.